08/06/11 - Tiling

The tiler (who is a smoker!) has started.  He's doing a really good job but he keeps leaving cigarette butts everywhere!!

Laundry


Toilet


Ensuite

Laundry tub 

28/05/11 - Garage Door

The Garage Door has been installed. 
It's a panel lift in WOODLAND GREY.




Can't wait til they clean up all the rubbish!!  They are grots!

28/05/11 - Stacker Sliding Door

The glass has been put in on our big stacker sliding door.


Friday, May 20, 2011

22/05/11 - Sorrento Bagging

They have started on the external colours.  The Granosite Sorrento finish in SLATE by Wattyl has been put on the external brickwork.
It matches well with our GUNMETAL roof tiles by Boral.  Fascia is Colourbond DUNE and guttering is Colourbond WOODLAND GREY.  Windows are also WOODLAND GREY.



20/05/11 - Stairs

The stairs have been installed. 
They are not quite right but hopefully they'll be fixed.







18/05/11 - Doors & Skirtings

Marcello the chippie has started to hand the doors.  Architrave and skirting boards are also going on. 




01/05/11 = Gyprock & Insulation

There was a bit of a panic when we found out that the gyprockers would be starting because Matt hadn't run the TV and intercom cables.  But the boys got it done and the gyprockers have started!

Shane's TV Room

Boys toy Room

Kitchen - Pantry 

Garage

Studio Room (upstairs) 

Ensuite

Bed 2



04/04/11 - Roof Tiles

The roof is on! 




Wednesday, March 30, 2011

23/03/11 - Garage Slab

The "suspended slab" for the garage has been poured.




Our "cellar" under the garage slab