Friday, May 20, 2011

22/05/11 - Sorrento Bagging

They have started on the external colours.  The Granosite Sorrento finish in SLATE by Wattyl has been put on the external brickwork.
It matches well with our GUNMETAL roof tiles by Boral.  Fascia is Colourbond DUNE and guttering is Colourbond WOODLAND GREY.  Windows are also WOODLAND GREY.



20/05/11 - Stairs

The stairs have been installed. 
They are not quite right but hopefully they'll be fixed.







18/05/11 - Doors & Skirtings

Marcello the chippie has started to hand the doors.  Architrave and skirting boards are also going on. 




01/05/11 = Gyprock & Insulation

There was a bit of a panic when we found out that the gyprockers would be starting because Matt hadn't run the TV and intercom cables.  But the boys got it done and the gyprockers have started!

Shane's TV Room

Boys toy Room

Kitchen - Pantry 

Garage

Studio Room (upstairs) 

Ensuite

Bed 2



04/04/11 - Roof Tiles

The roof is on!